California State University Fresno
Fresno, California
Schedule & Budget Management
Pre-Design Administration
Procurement
Design Administration
Construction Administration
Project Accounting
Project Management
$1.2 Millon Project Budget
10,800 SF
Six Month Construction Schedule
Architect: Darden Architects, Inc.
General Contractor: Lou Conte
In February 1995, the space constraints caused by the growth in athletic programs and the need for competitive facilities, led California State University, Fresno Athletic Corporation to explore the feasibility of constructing a new Strength and Conditioning Center. PMA developed a procurement and implementation strategy to effectively control the project cost and meet the schedule objectives for athletic recruiting. Construction on the 10,800 sq.ft. Strength and Conditioning Center was completed in 6 months at a project cost of $1.2 million, including equipment.